TCH.1C-27J-2-27JG
2-10.1
figure
) and (refer to figure
6.Remove plates (11) from fairleads (10) by removing
bolts (9), washers (13) and self locking nuts (12).
Discard removed self locking nuts.
7.Remove from LH (RH) pulleys between ribs 23 and 24
(34) cable-lock clevis (38) by removing pins (35),
washers flat (37) and cotter pins (36). Discard
removed cotter pins.
8.Remove LH (RH) upper fairleads (29) by removing
bolts (30), washers (28) and self locking nuts (27).
Discard removed self locking nuts.
9.Remove the retaining clips (21, 23, 24 and 31) then,
acting on the turnbuckles (22, 25 and 32), release the
cable tension of all cable stretches (3).
10.Loosen completely the turnbuckles (22, 25 and 32)
then remove all cable stretches (3) from LH pulley in
center wing section (2), aft pulley (15) and LH (RH)
pulleys between ribs 23 and 24 (34).
2-10.2
) ,
) , (refer to figure
)
1.Install cable stretch (3) on LH (RH) pulleys between
ribs 23 and 24 (34).
2.Position the cable stretch (3) in the grooves of the
other pulleys (26).
3.Install cable stretch (3) on LH pulleys (2) in the center
wing section and in Aft pulley (15).
4.Insert cable stretch (3) in the fairleads (10) and
connect plates (11) by using bolts (9), washers (13)
and new self locking nuts (12) (LCM NO. 00011).
5.Insert cable stretch (3) in LH (RH) upper fairleads (29)
and tighten bolts (30), washers (28) and new self
locking nuts (27)(LCM NO. 00011).
(Cont'd)
27-10-05
2-69