TCH.1C-27J-2-27JG
2-56.2
INSTALLATION (refer to figure
)
and (refer to figure
3.Hold the Pitch trim actuator (drive) (18), insert the bolt
(26), washers (24 and 25) and castellated nut (22),
then torque tighten to 90 - 100 in lb (AGE NO. 00054).
4.Insert new cotter pin (23) in the Pitch trim actuator
(drive) connections.
5.Connect the Pitch trim actuator (drive) (18) to the
shaft (16) that join Pitch trim actuator (drive) (18) to
Pitch trim actuator (slave) (17).
6.Reconnect the bonding lead (28) using bolt (11) and
washer (29) then Torque tighten the bolt to 8 - 10 In lb
(AGE NO. 00054).
NOTE
Remove protection caps from the electrical
connectors to be installed.
7.Connect the two electrical connectors (10CGA and
10CGB) (20 and 21) to the Pitch trim actuator (drive)
(18).
8.Remove rigging pins (3, 6, 8 and 9) (AGE NO. 00181)
from control wheel (2), the rear elevator axles (4 and
10) and the Pitch Feel Trim Units (5 and 7).
FOLLOW ON MAINTENANCE:
1.Close thermal insulation screen.
2.Enable Cargo Ramp Function.
3.Restore hydraulic power system (refer to manual
4.Connect electrical power to aircraft (refer to manual
Perform the functional test:
) .
27-30-40
2-469