TCH.1C-27J-2-27JG
2-60.2
INSTALLATION. Proceed as follows:
A.Ensure that the L and R rear quadrants are to
neutral position (rigging pins inserted).
B.Install the J.O.M. assy on the support structure and
lock it in neutral position with the proper rigging pin
dia 7.95 mm.
C.Screw 16 bolts that fix J.O.M. with aircraft structure
(4 on R connection, 4 on L connection, 4 onR
intermediate connection and 4 on L intermediate
connection).
D.Reconnect the two rods on the extremity of the
J.O.M.
E.Position the bushing, position the washers, insert
the bolt and position the nut, then Torque tighten
on connection rods the two bolts (1 for R and 1 for
L).
F.Reconnect the elctrical connector on the center of
J.O.M.
G.Remove all rigging pins previuosly inserted.
FOLLOW ON MAINTENANCE:
1.Close thermal Insulation Screen.
2.Enable Cargo Ramp.
3.Restore hydraulic power system (refer to manual
4.Connect electrical power to aircraft (refer to manual
5.Perform the functional test:
27-30-50
2-489