2-51.2 INSTALLATION. To install the control wheel
proceed as follows: (Cont'd)
B.On the control column carefully insert the Control
wheel wire harness through control column, until
reaching the bottom of the control column (cockpit
underfloor), if it necessary replace tie wraps
previously removed, then re-insert the pins into the
connector (51VEA Pilot side or 52VEA
Copilotside).
C.Torque tighten the bolt to 430 lb in and lock the
key washer in order to fix the control wheel.
D.Connect the electrical connector (51VEA Pilot Side
or 52VEA Copilot side) on the bottom of the control
column (cokpit underfloor).
FOLLOW ON MAINTENANCE:
1.Install the Chart Holder (refer to manual
) .
2.Close the access panels 711A, 712A, 130B and
130C.
3.Perform a functional check MEASUREMENT OF
AILERON MANOEUVRE EFFORT (refer to para
)
, ADJUSTMENT PILOT (COPILOT) CONTROL
STICK TO FORWARD QUADRANT (refer to para